By registering with our site you will have full instant access to:
268,000 posts on every subject imaginable contributed by 1000's of members worldwide.
25000 photos and videos mainly relating to the British Merchant Navy.
Members experienced in research to help you find out about friends and relatives who served.
The camaraderie of 1000's of ex Merchant Seamen who use the site for recreation & nostalgia.
Here we are all equal whether ex Deck Boy or Commodore of the Fleet.
A wealth of experience and expertise from all departments spanning 70+ years.
It is simple to register and membership is absolutely free.
N.B. If you are going to be requesting help from one of the forums with finding historical details of a relative
please include as much information as possible to help members assist you. We certainly need full names,
date and place of birth / death where possible plus any other details you have such as discharge book numbers etc.
Please post all questions onto the appropriate forum
On Behalf of Brian, Mike, Myself and the team may we wish you all a very "MERRY CHRISTMAS" for 2024. Enjoy the festivities and wherever you go, please return safely
-
28th November 2024, 08:35 PM
#1
Latest Glen Sannox Delay
Although the Ship has now been handed over and is now in process of Berthing and bunker trials.
The latest delay which caused her handover to Cmal 4 days, was a faulty anchor.
They reckoned that they could lower the anchor but not raise it (Brewers droop?).
A temporary fix has been deployed until a permanent solution is available.
Vic
R879855
-
Post Thanks / Like
-
29th November 2024, 12:22 AM
#2
Re: Latest Glen Sannox Delay
HI Vic
What did they do shove a deck boy down the Hawse pipe to guide it in.
Des
R510868
Lest We Forget
-
Post Thanks / Like
-
29th November 2024, 12:36 AM
#3
Re: Latest Glen Sannox Delay
The only ships I saw with problems with anchor stowage were deep sea vessels with so called self stowage lockers ? The average tramp ship had 8/15 on one anchor and 9/15 on the other. Where I never saw a problem with anchor stowage were cable stowage was off shore where cable lengths were 29/15 or 30/15 (shackles)
The problem to me was lack of foresight on the locker design I.E . The size of the lockers. In the case of the deep water vessels a hand with a broom handle was usually required at the chain locker door to push the cable into the confined space. JS
Last edited by j.sabourn; 29th November 2024 at 12:38 AM.
R575129
-
Post Thanks / Like
-
29th November 2024, 09:18 AM
#4
Re: Latest Glen Sannox Delay
Down at the chain locker with a broom handle ? , wow that takes me back to my apprentice days .
-
Post Thanks / Like
-
29th November 2024, 10:05 AM
#5
Re: Latest Glen Sannox Delay
Was easier if still had the broom head on . JS
R575129
-
Post Thanks / Like
-
29th November 2024, 10:43 AM
#6
Re: Latest Glen Sannox Delay
Do not if these facts are correct as they are from Wikipedia.
£97 million original contract for two ferries. £380 million as of June 2024, and £45 million loan written off.
Ordered October 2015, Laid down February 2017 and Launched Novemeber 2017.
https://www.bbc.co.uk/news/uk-scotla...-west-66945640
As the old saying goes lessons will be learnt. From one of the greatest ship building nations in the world to an absolute laughing stock.
Camell Lairds also when they built the research vessel Sir David Attenborough 3 years later and millions over budget. Be interesting to see haw they get on with the new Mersey Ferry they have started building last month.
Best not mention the Aircraft Carriers the RN got £7billion what a joke.
-
Post Thanks / Like
-
29th November 2024, 11:53 AM
#7
Re: Latest Glen Sannox Delay
Read somewhere the problem with the anchor was down to the gypsy wheel, not the cable storage. Possibility of the cable links either not sitting on the gypsy correctly or the lead from the hawse to the gypsy not being aligned correctly.
Rgds
J.A
-
Post Thanks / Like
-
29th November 2024, 02:59 PM
#8
Re: Latest Glen Sannox Delay
In the heyday of British Shipbuilding, the yards had their own design and Naval Architects, now seems it's all done abroad.
The Romanian Design team sent 20,000 drawings to Fergusons during the pandemic.
What happened to in house teams?
Vic
R879855
-
Post Thanks / Like
-
29th November 2024, 10:14 PM
#9
Re: Latest Glen Sannox Delay
I know when I started with Ocean they had their own inhouse naval architect department. I am sure that the first generation OCL Bay Boats were designed in India buildings and the design was put out to tender.
When serving my time at Lairds I spent time in the drawing office.
-
Post Thanks / Like
-
30th November 2024, 07:05 AM
#10
Re: Latest Glen Sannox Delay
#1 Vic it was usual years ago on ships as I was on that the actual handing over after trials was not the end of the matter. There was usually a clause in the agreement that the ship until the final building fees were handed over that the ship to all intents and purposes still belonged to the builders yard. The final instalments were usually paid about 12 months ,after at the guarantee Drydock. I was on the Maratha Envoy built by Mitsibuishi in Yokohama , however the gurantee drydock ran on to 18 months later than normal , so my repair and alterations list was longer and there were quiete a few things to alter and they did get done after the usual arguments . However the plaque in the wheelhouse saying the vessel belonged to the builders yard finally came down and all monies paid .Cheers JS
R575129
-
Post Thanks / Like
Tags for this Thread
Posting Permissions
- You may not post new threads
- You may not post replies
- You may not post attachments
- You may not edit your posts
-
Forum Rules